StrategyNov 3, 202615 min readBy Jamieson Hill

Reserving Data Center Capacity for GPUs on Order: Lead Times and Timelines

Reserve liquid-cooled data center capacity 12 to 24 months before your GPUs arrive. In 2026 more than 80% of the space under construction in primary US markets is already preleased, most tenants signing today are contracting for 2028 deliveries, and NVIDIA expects GPU supply to stay a bottleneck into 2028. The date that decides a deployment is when power, cooling and a commissioned hall meet the hardware. This guide sets out the lead times, the contract terms and a month-by-month plan.

Lead times that decide when GPUs on order can run, in weeks, as of 2026. A new grid connection in primary US markets takes more than 208 weeks, generator step-up transformers more than 160, large power transformers 128, high-voltage breakers 125 and switchgear 44, while a factory-built data hall takes about 20 to 39 weeks and NVIDIA's DSX POD cuts on-site deployment from about 26 weeks to 2 at a prepared site; 80.4 percent of primary-market space under construction is already preleased.
Power and long-lead gear, not GPUs, set the date for GPUs on order. Sources: JLL Jan and Aug 2026; Wood Mackenzie via POWER Jan 2026 and Reuters Jul 2026; BladeRoom 2026; Flex Oct 2026; NVIDIA Aug and Oct 2026; CBRE Aug 2026. © GR1D — free to republish with a link to this article.Full size ↗
Read as text
  • Power and long-lead gear, not GPUs, set the date
  • What decides when GPUs on order can run in 2026, and how much of the space is already taken.
  • Lead times, in weeks · Averages and vendor schedules as published; bars to scale from 0 to 210 weeks (4 years is about 208). · New grid connection · primary US markets (JLL) · >208 wk · Generator step-up transformer · by Q1 2026 (Wood Mackenzie) · >160 wk · Large power transformer · Q2 2025 average (Wood Mackenzie) · 128 wk · High-voltage breaker · H2 2025 (Reuters) · 125 wk · Switchgear · Q2 2025 average (Wood Mackenzie) · 44 wk · Factory-built data hall · vendor schedules (BladeRoom; Flex) · 20–39 wk · DSX POD on-site deployment · at a prepared site (NVIDIA) · 26 → 2 wk · A factory-built hall saves on-site weeks only once power, switchgear and permits are in hand. Without them, the top fou
  • Already spoken for · The space and the GPUs are both booked ahead. · 80.4% · of primary-market space under construction preleased, H1 2026 (CBRE) · 1.4% · primary-market vacancy, a record low (CBRE) · 2028 · deliveries most tenants signing today contract for (JLL) · Jan 2028 · NVIDIA expects supply to stay a bottleneck at least through its fiscal 2028; Vera Rubin shipping since Aug 2026 · GR1D analysis: reserve liquid-cooled space 12 to 24 months before the GPUs arrive.

How far ahead should you reserve data center capacity for GPUs?

In 2026, reserve liquid-cooled capacity 12 to 24 months before your GPUs arrive: more than 80% of primary-market space under construction is already preleased (CBRE, Aug 2026).

CBRE's first-half 2026 survey found primary-market vacancy at a record low of 1.4%, 7,481.1 MW under construction, and commitments on 80.4% of it, up from 74.3% a year earlier. Less than 1,500 MW of future capacity remained available, "representing approximately six months of demand at the current absorption rate." Asking rates rose 8.3% for 3–10 MW deployments and 6.7% for 10 MW and up in the half (CBRE, Aug 2026).

JLL counts more than 66 GW under construction in North America, 77% of it in frontier markets, with vacancy at 1% for the third consecutive year, and its midyear report says "Most tenants securing space today are contracting for 2028 deliveries" (JLL, Aug 2026). Across the Americas, Cushman & Wakefield counts 37.7 GW under construction, "with 91.7% precommitted prior to delivery" (Cushman & Wakefield, Sep 2026).

How far ahead data center tenants commit, by deal type and market, as reported in 2026 (2023 for the hyperscaler benchmark).
Deal type or marketHow far ahead of delivery tenants commitSource
Turnkey space, single tenant (Atlanta)About one year before completionData Center Frontier, citing CBRE, Aug 2026
Build-to-suit (Atlanta)About two and a half years aheadData Center Frontier, Aug 2026
Northern VirginiaAll 2026 deliveries already committed; preleasing "deeper into 2027 and beyond"Data Center Frontier, Aug 2026
North America, new leasesMostly for 2028 deliveriesJLL, Aug 2026
Dallas–Fort Worth95% of the 765+ MW under construction preleased; vacancy 2.8%Dallas Innovates, citing CBRE, Sep 2026
Hyperscalers, 2023 benchmark24–36 months ahead, up from 12–18 months the year beforeDatacenterDynamics, citing TD Cowen, 2023

For a tenant with GPUs on order, the space decision comes before the delivery window in the purchase order, not after it. A turnkey hall about a year out is the short end. Anything larger than a few megawatts, or anything that needs a new building, sits at the long end, and the long-lead steps behind it are laid out in how a data center is built.

How long do GB300 and Vera Rubin systems take to arrive?

In 2026 no NVIDIA partner publishes a GB300 NVL72 lead time, and NVIDIA expects supply to remain "a bottleneck at least through the end of fiscal year 2028" (NVIDIA, Aug 2026).

NVIDIA's fiscal 2028 ends in late January 2028. On the August 26, 2026 earnings call, CFO Colette Kress called the outlook "supply-constrained," said "We commenced production shipments of Vera Rubin earlier this month," and put Vera Rubin at about 20% of data center revenue in its fiscal third quarter, which ends in October (NVIDIA, Aug 2026). CoreWeave stood up a Vera Rubin NVL72 cluster for its customer Cognition in early September (CoreWeave, Sep 2026).

GB300 NVL72 is in volume production. Supermicro says it is "shipping volume SKUs across the GB300 NVL72" and took more than $60 billion of new orders in its June quarter (Supermicro, Aug 2026). Dell ended its July quarter with a $95 billion AI server backlog, and Futurum notes that supply "remains the main constraint" (Futurum, Sep 2026).

The parts behind the racks stay tight:

  • Memory: Micron expects conditions "much tighter in calendar 2027 and 2028 than they were in 2026" (Computerworld, Oct 2026), and SK hynix expects demand to exceed supply through 2030 (The Next Web, Oct 2026).
  • Packaging: TSMC's CoWoS supply "remains tight" (TrendForce, Oct 2026).
  • The next rack: Rubin Ultra's Kyber NVL144 rack is on NVIDIA's roadmap for 2027; SemiAnalysis reported a slip to 2028, and NVIDIA answered "Our roadmap is intact" (Tom's Hardware, Jul 2026).

The hardware is often not the long pole. Supermicro's June-quarter revenue came in at $11.1 billion "due to some short-term customer delays in power, cooling, and networking": servers were ready before the sites were (Supermicro, Aug 2026). Jensen Huang said the same from the other side on NVIDIA's call: "You've got to go secure the land, power, and shell, which oftentimes is a couple, two, three years out." At GTC Berlin he put the cost of a three-month delay on a 1 GW AI factory at about $10 billion of missed revenue (The Next Platform, Oct 2026). Treat the ship window in an OEM order as a range, get it in writing, and plan for the hall to be commissioned before its earliest date.

How long from purchase order to power-on with a prefab data center module?

In 2026, vendors quote about 20 to 39 weeks to deliver an operating factory-built AI data hall, and none of those schedules brings new grid power (BladeRoom, 2026; Unite.AI, Oct 2026).

Schedule claims for prefabricated and modular data halls, 2026. Each is a vendor's claim about its own product, and each assumes a prepared site.
ProductVendor's schedule claimConditionSource
NVIDIA DSX POD (Vera Rubin)On-site deployment "from six months to as little as 14 days"Connects to "a prepared site's power, cooling, networking"; partners deliver from early 2027NVIDIA, Oct 2026
BladeRoom modular data halls"Operational within 20 weeks"From final design agreementBladeRoom, 2026
Flex Axiom AI ModulesFrom 78 weeks to as few as 39Modeled against an 18-month build; results "vary based on project scope, site conditions"Unite.AI, Oct 2026
Eaton with FlexnodeDeployment schedules 35% shorter on averagePrefabricated halls of 3.5 to 35 MWEaton, Jan 2026
Vertiv OneCoreUp to 50% less on-site work, commissioning and time-to-tokenAgainst traditional buildsVertiv, Feb 2026
Schneider Electric RapidScale Reference Design 115On-site installation from 75.5 hours to 15 hours per podTime study with Compass DatacentersSchneider Electric, Oct 2026
Duos Edge AI and LG CNSA prefab unit in 60 or 90 days; about six months deployed, against two or three yearsPermits and site preparation set the paceIEEE Spectrum, Mar 2026

Every one of these schedules starts after the hard part. "Factory integration cannot create a power connection," reads a section heading from the modular vendor ModulEdge. Its illustrative schedule from design release runs 20 weeks of manufacturing and transport beside 28 weeks of site preparation, then 4 weeks of integration and acceptance, so site work, not the factory, sets the 32-week result (ModulEdge, Oct 2026). Futurum says the same of DSX POD: "onsite deployment can shrink from six months to 14 days once site utilities are ready," but "the binding constraint on AI factories in Europe is access to grid power, and DSX POD doesn't address that" (Futurum, Oct 2026). ABI Research makes the same point (ABI Research, Oct 2026).

What sets the date on a site that already has power?

GR1D analysis. Order to power-on for a factory-built AI hall on a site whose utility power is already energized:

GR1D analysis. Method: published 2025–2026 durations for each step; the critical path is the longer of manufacture and site preparation, plus integration and commissioning, with switchgear and transformers ordered first.
StepTypical duration, 2026On the critical path?Source
Module manufacture and transportAbout 20 weeksYes, unless site work runs longerBladeRoom; ModulEdge
Site preparation: pad, utilities, yardAbout 28 weeks in an illustrative scheduleYes; runs beside manufactureModulEdge, Oct 2026
Medium-voltage switchgear44 weeks average (Q2 2025)Yes, if not ordered before the modulesPOWER, Jan 2026
Large power transformer128 weeks average (Q2 2025)Sets the date if it is not on sitePOWER, Jan 2026
Integration and acceptanceAbout 4 weeks in the illustrative schedule; as little as 14 days on site for DSX PODYesModulEdge; NVIDIA, Oct 2026
Commissioning, Level 1 to integrated systems testNo published norm; needs liquid-cooled load banks and a clean loopYesASHRAE; DCD
GPU rack provisioning9 hours to multiple days per new NVL72 rackAt handoverSemiAnalysis, Nov 2025

On ModulEdge's illustrative numbers that path is 32 weeks from design release, about seven and a half months, plus whatever time the integrated systems test needs: inside the 6–12 months GR1D quotes for modular builds once power is in place (GR1D calculation). Without power in hand, the utility sets the date: JLL puts the average wait for a grid connection in primary US markets above four years (JLL, Jan 2026), and generator step-up transformer lead times passed 160 weeks by the first quarter of 2026 (Reuters via Kitco, Jul 2026). The full sequence for a conventional build is in realistic data center timelines.

Ladder of six ways to get GPUs running in 2026 and how long each takes: existing liquid-cooled colocation space in weeks to several months of fit-out at 1.4 percent vacancy; a GPU cloud contract in months; a prefab hall on a powered site in about 20 to 39 weeks plus commissioning; converting an air-cooled hall with delays beyond six months; a conventional build with power in hand in about 18 months for 50 MW; and a new grid connection in more than four years in primary markets, each with what must already exist.
Six paths to running GPUs, and what each needs in place. Sources: CBRE Aug 2026; JLL Jan 2026 and Aug 2025; BladeRoom 2026; Flex Oct 2026; CoreWeave 2026; GR1D analysis. © GR1D — free to republish with a link to this article.Full size ↗
Read as text
  • Six paths to running GPUs, and what each needs in place
  • Time from commitment to GPUs in service, 2026. Three paths fit inside about six months; each needs something that already exists.
  • ABOUT 6 MONTHS OR LESS · LONGER · YEARS
  • ABOUT 6 MONTHS OR LESS
  • LONGER
  • YEARS
  • Existing liquid-cooled colocation
  • Weeks to months · of fit-out, now stretching from weeks to several months
  • of fit-out, now stretching from weeks to several months
  • NEEDS · A provider with liquid-ready space free, at 1.4% vacancy
  • NEEDS
  • RISK · Scarcity; take-or-pay floors of 60–85% of allocated power
  • RISK
  • CBRE (Aug 2026)
  • GPU cloud, reserved capacity
  • Months · for a provider to stand up high-density capacity
  • for a provider to stand up high-density capacity
  • NEEDS · A provider with a spare cluster of the right GPU
  • RISK · Multi-year take-or-pay; CoreWeave's contracts average about 5 years
  • JLL (Aug 2025); CoreWeave 10-K (2026)
  • Prefab hall on a powered site
  • 20–39 weeks · vendor schedules, plus commissioning
  • vendor schedules, plus commissioning
  • NEEDS · Power, switchgear, permits and a pad already in hand
  • RISK · Long-lead electrical gear; permits
  • BladeRoom (2026); Flex via Unite.AI (Oct 2026)
  • Converting an air-cooled hall
  • 6+ months · delays "can extend beyond six months"
  • delays "can extend beyond six months"
  • NEEDS · An air-cooled hall with spare power
  • RISK · CDU, piping and floor retrofit
  • Conventional build, power in hand
  • About 18 months · average for a 50 MW facility
  • average for a 50 MW facility
  • NEEDS · Power and permits
  • RISK · Equipment lead times: 42 weeks on average in the US
  • JLL (Jan 2026)
  • New grid connection
  • 4+ years · average wait in primary US markets
  • average wait in primary US markets
  • NEEDS · Nothing yet: land and an application
  • RISK · Utility studies, transformers and regulators

Is prefab the only way to get AI capacity in six months?

No. In 2026 the six-month options are liquid-ready space that already exists, a GPU cloud contract, or a prefab hall on a site with power in hand (GR1D analysis).

GR1D analysis of published 2025–2026 figures. Method: time runs from the tenant's commitment to GPUs in service; ranges are the sources' own.
PathTime to running GPUs, 2026What must already existMain riskSource
Existing liquid-cooled colocationWeeks to several months of fit-outA provider with liquid-ready space freeScarcity at 1.4% vacancy; take-or-payCBRE, Aug 2026
GPU cloud, reserved capacityMonthsA provider's spare clusterMulti-year take-or-pay; CoreWeave's contracts average about five yearsJLL, Aug 2025; CoreWeave 10-K
Prefab hall on a powered siteAbout 20–39 weeks, plus commissioningPower, switchgear, permits, a padLong-lead gear; permitsBladeRoom; Unite.AI
Converting an air-cooled hallDelays "beyond six months"An air-cooled hall with spare powerCDU, piping and floor retrofitCBRE, Aug 2026
Conventional build, power in handAbout 18 months for 50 MWPower and permitsEquipment: a 42-week average lead time in the USJLL, Jan 2026
New grid connectionMore than four years in primary marketsNothing yetUtility, transformers and regulatorsJLL, Jan 2026

The fastest builds on record reused something. NVIDIA says xAI and NVIDIA built Colossus in Memphis "in just 122 days," with 19 days from the first rack to training (NVIDIA, Oct 2024); Bisnow reports the site was a shuttered Electrolux factory, against about 15 months for other large training clusters (Bisnow, Sep 2025). Greenfield is slower: Crusoe began its Abilene, Texas campus in June 2024 and energized the first two buildings within a year (Crusoe, Sep 2025). IREN delivered Horizon 1 in Childress, Texas, 50 MW of direct-to-chip GB300 NVL72 capacity, to Microsoft in August 2026 under a contract announced in November 2025, about nine months later (GR1D calculation from IREN, Aug 2026).

A retrofit is not a shortcut either. CBRE warns that "for air-cooled data centers requiring conversion to liquid cooling, delays can extend beyond six months," and that ready-for-service fit-out dates "are expanding from weeks to several months" (CBRE, Aug 2026). A GB300 NVL72 needs 132–142 kW and a direct-to-chip loop per rack; the full list is in GB300 NVL72 colocation requirements.

What goes into a data center capacity reservation contract?

In 2026 a capacity reservation fixes the kW, a ready-for-service date, a ramp and a take-or-pay floor, typically 60–85% of allocated power, plus remedies for delay (CBRE, Aug 2026).

Terms to settle in a data center capacity reservation, with 2026 market signals.
TermWhat to pin down2026 market signalSource
Allocated powerkW per phase; billing on reserved or actual useAgreements should state "whether billing is based on reserved capacity or actual usage"Morgan Lewis, May 2026
Ready-for-service (RFS) dateDelivery milestones and the delays that excuse them"Parties should agree on delivery milestones up front"Vinson & Elkins, 2026
RampPhases, each tied to its own RFS dateOpenAI's leases carry "phased commencement tied to RFS conditions"SB Energy S-1, Aug 2026
Take-or-payA floor on paid utilization60% to 85% of allocated power, increasingly common in the USCBRE, Aug 2026
Delay remediesCredits, liquidated damages, a termination right"tiered credits and termination rights for RFS delays"; tenants reportedly asking more than $5 million a day on large dealsMorgan Lewis, May 2026; AI Weekly, citing The Information, Oct 2026
Term and renewalsInitial term and extension optionsA 15-year initial term is common; colocation commitments "sometimes extending up to a decade"Clifford Chance, Jul 2026; Morgan Lewis
Expansion rightsFirst offer on adjacent capacity"rights to adjacent capacity if applicable"Morgan Lewis, May 2026
Credit supportDeposit, letter of credit or parent guarantyOperators are "requiring stronger guarantees such as letters of credit or parent backing" from newer AI tenantsData Center Knowledge, Apr 2026
EscalatorFixed or indexed annual increase"Annual escalators, whether fixed or tied to an index, should be considered"Morgan Lewis, May 2026

Two of these moved this year. Delay penalties: The Information reported in October that tenants on large campuses now ask for more than $5 million a day for late delivery, up from about $1 million in the spring, and that one OpenAI lease gives a free day of rent for each day of delay, doubling after 90 days (AI Weekly, Oct 2026). Exit rights: termination for convenience in hyperscale leases is "starting to go away," a Vinson & Elkins partner told Facilities Dive (Facilities Dive, Aug 2026).

Agree which power figure each clause uses. A GB300 NVL72 is rated at 132 kW nominal and about 155 kW at peak (HPE, Sep 2026), so the kW commitment, the take-or-pay floor and any overage charge should all name the same basis; the powered-shell, turnkey and colocation trade-offs behind the choice of contract are in powered shell vs turnkey vs colocation.

What should you sign when for GPUs on order?

Work back from the GPU delivery date: shortlist sites with power in hand 18–24 months out, sign the reservation 12 or more months ahead, and commission before the racks arrive (GR1D analysis).

A reservation timeline that works back from GPU delivery: 18 to 24 months out, shortlist sites by power in hand and get the energization date in writing; 12 to 18 months out, sign the reservation with kW, ready-for-service date, ramp, take-or-pay and delay remedies while the provider orders switchgear and transformers; 9 to 12 months out, freeze the rack spec; 6 to 9 months out, confirm the ship window as modules are built; 1 to 3 months out, witness commissioning with liquid-cooled load banks; at delivery, provision and burn in each rack.
What to sign when, working back from GPU delivery. Sources: JLL Aug 2026; CBRE Aug 2026; Wood Mackenzie via POWER Jan 2026; BladeRoom 2026; ASHRAE; SemiAnalysis Nov 2025; GR1D analysis. © GR1D — free to republish with a link to this article.Full size ↗
Read as text
  • What to sign when, working back from GPU delivery
  • Each step starts as early as the work it unlocks takes to finish. Months are counted back from the day the GPU racks arrive.
  • 18–24 months out · Shortlist by power in hand · TENANTGet each site's energization and go-live dates in writing · PROVIDERShares utility, permit and equipment status, dated · Most tenants signing today contract for 2028 deliveries (JLL)
  • 12–18 months out · Sign the reservation · TENANTkW, ready-for-service date, ramp, take-or-pay, delay remedies · PROVIDEROrders switchgear and transformers if not on site · Switchgear 44 weeks, power transformers 128 (Wood Mackenzie)
  • 9–12 months out · Freeze the rack spec · TENANTkW per rack, coolant temperature and flow, floor load, network · PROVIDERReleases the hall or module design · GB300 NVL72: 132 kW nominal, about 155 kW at peak (HPE)
  • 6–9 months out · Confirm the ship window · TENANTOEM delivery range in writing; order optics and cabling · PROVIDERBuilds modules and prepares the site in parallel · About 20 weeks of factory time (BladeRoom)
  • 1–3 months out · Witness commissioning · TENANTLiquid-cooled load banks, flush and fill, integrated test · PROVIDERRuns Level 1 to Level 5 commissioning · Dirty coolant "can result in extensive project delays" (ASHRAE)
  • Delivery day · Provision and burn in · TENANTReceives, provisions and burns in each rack · PROVIDERHands over power and cooling at the contracted spec · 9 hours to multiple days per new NVL72 rack (SemiAnalysis)
  • Two dates to ask for · Every provider has a lead time from order and a site go-live date. The later of the two is yours; a reservation that names neither is a waiting list.
  • Two dates to ask for
  • Every provider has a lead time from order and a site go-live date. The later of the two is yours; a reservation that names neither is a waiting list.
GR1D analysis: a reservation plan for GPUs on order. Method: each step's lead is the published duration of the work it starts, plus slack for approvals.
Months before GPUs arriveTenantProviderWhy
18–24Shortlist sites with power in hand; get each site's energization and go-live dates in writingShares utility, permit and equipment status, datedMost tenants signing in 2026 contract for 2028 deliveries (JLL)
12–18Sign the reservation: kW, RFS date, ramp, take-or-pay, delay remedies, credit supportOrders switchgear and transformers if they are not on siteSwitchgear averages 44 weeks and power transformers 128 (POWER)
9–12Freeze the rack spec: kW per rack, coolant temperature and flow, floor load, networkReleases the hall or module designA design change after release restarts factory work
6–9Confirm the OEM ship window; order optics and cablingBuilds modules and prepares the site in parallelAbout 20 weeks of factory time (BladeRoom)
1–3Witness commissioning: liquid-cooled load banks, flush and fill, integrated systems testRuns Level 1 to Level 5 commissioningPoor fluid cleanliness "can result in extensive project delays" (ASHRAE)
0Receive, provision and burn in each rackHands over power and cooling at the contracted spec9 hours to multiple days per new NVL72 rack (SemiAnalysis)

Ask every provider for two dates: the lead time from order, and the site's own go-live. The later of the two is yours. A reservation that names neither is a waiting list.

What can push a capacity date in Texas?

In Texas in 2026 the dates most at risk are power dates: ERCOT paused energization approvals for computational loads of 75 MW or more on August 3, 2026 (ERCOT, Sep 11, 2026).

The national record says to expect slippage. JLL found that 57% of data center projects had a construction delay of three months or more in 2025 (JLL, Jan 2026); Sightline Climate expects 30 to 50% of the 140 projects (16 GW) planned for 2026 to slip to 2027 or later (E&E News, Feb 2026); and high-voltage breakers reached 125 weeks in the second half of 2025, against 77 weeks in 2023 (Reuters via Kitco, Jul 2026).

Before you sign in Texas, ask for:

  1. The energization date in an executed agreement, not a queue position, and whether the site's load is above or below ERCOT's 75 MW line (ERCOT large-load interconnection).
  2. Which permits are issued and which are applied for. Under the TCEQ pause, an application on file is not a permit.
  3. The long-lead equipment on order, with the factory's delivery dates.
  4. The site's evidence against the four-rung ladder in AI data center site selection in Texas.

Frequently asked questions

How far in advance should I reserve colocation for GPUs?

In 2026, 12 to 24 months before the hardware arrives. More than 80% of primary-market space under construction is preleased (CBRE, Aug 2026), and most tenants signing now are contracting for 2028 deliveries (JLL). Turnkey space has been preleased about a year before completion, build-to-suit about two and a half years ahead.

How long does it take to get a GB300 NVL72 after ordering?

No NVIDIA partner publishes a standard lead time. GB300 NVL72 ships in volume, Vera Rubin production shipments began in August 2026, and NVIDIA expects supply to stay a bottleneck through at least its fiscal 2028, which ends in January 2028. Get the ship window in writing and have the hall commissioned first.

How long does a prefab data center module take from order to power-on?

Vendors quote about 20 to 39 weeks to deliver an operating factory-built hall, and NVIDIA's DSX POD cuts on-site deployment to as little as 14 days, but only at a site whose power, cooling and permits are ready. With power in place, modular builds take 6–12 months; without it, the grid sets the date.

Can I get AI data center capacity in six months?

Yes, if something already exists: liquid-ready colocation space, a GPU cloud contract, or a powered site for a prefab hall. xAI's first Colossus cluster took 122 days in a converted factory. Converting an air-cooled hall to liquid cooling can add delays beyond six months (CBRE, Aug 2026).

What is a take-or-pay clause in a colocation contract?

A minimum the tenant pays whether or not it uses the power it reserved. CBRE says these floors are becoming common in the US, at 60% to 85% of allocated power (Aug 2026). Agree whether the floor applies from the ready-for-service date or only after the ramp.

What happens if the data center isn't ready when my GPUs arrive?

That depends on the contract. Colocation agreements can carry tiered credits and termination rights for missed ready-for-service dates (Morgan Lewis, May 2026), and tenants on large campuses were reported in October 2026 to be asking for more than $5 million a day for late delivery. Without those clauses, the tenant carries the idle hardware.

Sources

  1. North America Data Center Trends H1 2026 — CBRE, 2026-08-27
  2. North America Data Center Report, Midyear 2026 — JLL, 2026-08-11
  3. Americas Data Center Update, H1 2026 — Cushman & Wakefield, 2026-09-14
  4. CBRE: Record Data Center Construction Fails to Ease Capacity Crunch — Data Center Frontier, 2026-08-28
  5. DFW Data Center Demand Remains Hot as Pre-Leasing Hits 95% — Dallas Innovates, 2026-09-03
  6. TD Cowen: AI demand caused 2.1GW of US data center leases in 90 days — DatacenterDynamics, 2023
  7. NVIDIA Q2 Fiscal 2027 Earnings Call Transcript — NVIDIA, 2026-08-26
  8. CoreWeave Delivers NVIDIA Vera Rubin NVL72 Performance at Production Scale, Starting With Cognition — CoreWeave, 2026-09-30
  9. Fourth Quarter Fiscal 2026 Prepared Remarks — Super Micro Computer, 2026-08-11
  10. Dell Technologies Q2 FY 2027: AI Orders Fuel Server and Storage Growth — Futurum, 2026-09-09
  11. Memory squeeze set to tighten through 2028, Micron says — Computerworld, 2026-10-01
  12. SK Hynix says memory shortage will last to 2030 — The Next Web, 2026-10-28
  13. TSMC Reportedly Eyes 20% CoWoS Price Hike Amid AI Demand Surge — TrendForce, 2026-10-27
  14. Nvidia's Kyber rack for Rubin Ultra reportedly delayed to 2028 — Tom's Hardware, 2026-07-06
  15. Huang shrugs off protestors to kick off GTC Berlin with DSX pods, robots — The Next Platform, 2026-10-21
  16. NVIDIA Introduces DSX POD AI Factories to Accelerate Europe's Infrastructure Deployment — NVIDIA, 2026-10-21
  17. Modular Data Centres — BladeRoom, 2026-06-01
  18. Flex Adds Factory-Built AI Modules to Modular Data Center Portfolio — Unite.AI, 2026-10-12
  19. Eaton Expands Modular Data Center Offering for Rapid Deployment of AI Factories From Grid to Chip — Eaton via Business Wire, 2026-01-28
  20. Vertiv Industrializes AI Deployment with Digitally Orchestrated Infrastructure — Vertiv via Nasdaq, 2026-02-26
  21. Schneider Electric unveils new prefabricated reference design — Schneider Electric via GlobeNewswire, 2026-10-21
  22. Modular data centers: Duos Edge AI and LG CNS — IEEE Spectrum, 2026-03-30
  23. NVIDIA DSX POD: Modular AI Factory Deployment — ModulEdge, 2026-10-21
  24. At GTC Berlin, NVIDIA Puts the AI Factory in an Actual Container — Futurum, 2026-10-22
  25. NVIDIA's DSX POD: Closing the Compute Infrastructure Gap — ABI Research, 2026-10-26
  26. Transformers in 2026: Shortage, Scramble, or Self-Inflicted Crisis? — POWER Magazine, 2026-01-02
  27. Commissioning and Performance Validation, AI Data Center Framework — ASHRAE
  28. How AI is reshaping data center power testing and commissioning — DatacenterDynamics
  29. ClusterMAX 2.0: The Industry Standard GPU Cloud Rating System — SemiAnalysis, 2025-11-06
  30. 2026 Global Data Center Outlook — JLL, 2026-01-08
  31. US power companies scramble to secure equipment as surging data center demand strains supplies — Reuters via Kitco, 2026-07-09
  32. The rise of Neocloud in the AI landscape — JLL, 2025-08-26
  33. CoreWeave, Inc. Form 10-K, fiscal year 2025 — CoreWeave via SEC, 2026
  34. NVIDIA Ethernet Networking Accelerates World's Largest AI Supercomputer, Built by xAI — NVIDIA, 2024-10-28
  35. Musk's xAI Building Massive Memphis Data Center Hub At Record Speed — Bisnow, 2025-09-18
  36. Crusoe Announces Flagship Abilene Data Center Is Live — Crusoe, 2025-09-30
  37. IREN Delivers Horizon 1 to Microsoft and Achieves NVIDIA Exemplar Cloud Status on GB300 NVL72 — IREN, 2026-08-13
  38. Activating the Colo Model: What Really Matters in Data Center Colocation Agreements — Morgan Lewis, 2026-05-18
  39. Data Center Leasing: 5 Strategies for Navigating Today's Market — Vinson & Elkins, 2026
  40. SB Energy, Inc. Form S-1 — SB Energy via SEC, 2026-08-31
  41. Data Center Late Fees Jump to $5M a Day, Marsh Rolls Out Cover — AI Weekly, citing The Information, 2026-10-25
  42. The Data Center Lease Is the Bond — Clifford Chance, 2026-07
  43. Neocloud Storm Gathers as Data Center Deals Stall Over Credit Risk — Data Center Knowledge, 2026-04-06
  44. Landlords flex rental power as data center viability becomes 'everybody's problem' — Facilities Dive, 2026-08-31
  45. Batch Zero Update, ERCOT Board Item 14 — ERCOT, 2026-09-11
  46. Texas Large Load Interconnection Update: ERCOT Batch Zero Pause and Verification Process — Baker Botts via Mondaq, 2026-08
  47. Governor Abbott Orders TCEQ to Pause All Permit Issuance for Data Center Projects — Bracewell, 2026-09-23
  48. TCEQ Backtracks, Suspends Data Center Permits Issued After Investigation Shows It Ignored Abbott's Pause — Public Citizen, 2026-10-22
  49. Texas data center permits: TCEQ suspends approvals — Texas Tribune, 2026-10-21
  50. Report: Data center construction delays grow — E&E News, 2026-02-24
  51. HPE NVIDIA GB300 NVL72 QuickSpecs — HPE, 2026-09-08
Jamieson Hill
Founder, GR1D

Jamieson Hill is the founder of GR1D, a Texas developer of powered-shell and turnkey AI data centers. He leads site acquisition, power procurement, joint-venture structuring and vendor negotiation across GR1D's 20 MW to 370 MW pipeline in South Houston, East Austin and North Texas.